Software Release Policy

This document doesn't talk about technical details of how to do a release. The release process is discussed elsewhere.

Software Repositories

The Software Team maintains five primary software repositories

  1. osg-development: This is the "wild west", the place where software goes while it is being worked on by the software team.
  2. osg-testing: This is where software goes when it is ready for wide-spread testing.
  3. osg-prerelease: This is where software goes just before being released, for final verification.
  4. osg-release: This is the official, production release of the software stack. This is the main repository for end-users.
  5. osg-contrib: This is where software goes that is not officially supported by the OSG Software Team, but we provide as a convenience for software our users might find useful.

We also create a repository per release, called osg-release-VERSION (such as osg-release-3.0.4). This is intended mostly for testing purposes, though users may occasionally find it useful.

Occasionally there may be other repositories for specific short-term purposes.

Version Numbers

There is a single version number that is used to summarize the contents of the osg-release repository. Having a single version number is very useful for a variety of reasons, including:

  1. Every time changes are made to the osg-release repository, we update the version number and write release notes.
  2. We have a shorthand for referring to the state of the repository; we can talk about specific releases.

However, there are important caveats about the version number:

  1. Even if a user says they have installed Version X, it may not be an accurate reflection of what they have installed: they may have chosen to update some of their software from a previous version. To truly understand what they have installed, the entire set of RPMs installed on their computer must be considered.
  2. The version number is only meaningful in the osg-release repository, though for technical reasons it's present (as an RPM) in other repositories.

The version number is communicated in two ways:

  1. Every time a new release is made, the version number is updated. All release notes and communication to users about this release uses the new version number.
  2. There is an osg-version RPM that reports the version of the release. Major metapackages (osg-ce, osg-client, etc...) depend on this RPM. The RPM itself has the version number in it. It also provide a program that reports the version, and a text file that contains the version number.

The version number will be of the form X.Y.Z. As of this writing, version numbers are 3.0.Z, where Z indicates a minor revision.

Progression of repositories

This figure shows the progression of repositories that packages will go through:

 osg-development -> osg-testing -> osg-prerelease -> osg-release
                  \
                   -> osg-contrib

Release policies

Adding packages to osg-development

New packages will only be added to osg-development with the permission of the OSG Software Manager. Updates can be done at any time without permission, but developers should be careful if their updates might be significant, particularly if an update might cause series compatibility issues. In cases where there is uncertainty, discuss it with the Software Manager.

Moving packages to osg-testing

A package may be moved from osg-development to osg-testing when the individual maintainer of that package decides that it is ready for widespread testing and when the package is eventually intended for a production release, and when approved by the OSG Software Manager. Approval is needed because this is when we first make packages available to people outside of the OSG Software Team.

Moving packages to osg-prerelease; Readying the release

When we are ready to make a production release, we first move the correct subset of packages from osg-testing into osg-prerelease. This should be done after checking with the OSG Release Manager to verify that it's okay to release the software. The intention of osg-prerelease is to do a final verification that we have the correct set of packages for release and that they really work together. This is important because the osg-testing repository might contain a mix of packages that are ready for release with packages that are not ready for release. When moving packages to osg-prerelease, the team member doing the release will:

  • Update the osg-version RPM to reflect the new version. Push this RPM through osg-development, osg-testing, and into osg-prerelease.
  • Find the correct set of packages to push from osg-testing into osg-prerelease.
  • At a minimum, run the automated test suite on the contents of osg-prerelease. In cases were more extensive testing is needed, or the test suite doesn't sufficiently cover the testing needs, do specific ad-hoc testing. (If appropriate, consider proposing extensions to the automated test suite.)

We expect that in most cases, this process of updating and testing the osg-prelease repository will be less than one day. If there are urgent security updates to release, this process may be shortened.

Note that, except in exceptional circumstances, we release software on Tuesdays. Therefore the osg-prerelease cache is probably updated and readied on a Monday (or perhaps late the previous week).

Moving packages to osg-release

Note that, except in exceptional circumstances, we release software on Tuesdays, so this process will only happen on Tuesdays.

When the osg-prerelease repository has been updated and verified, all of the changed software can be moved into the osg-release repository. As part of this move, two important tasks must be done:

  1. Record the complete set of packages in the new release repository.
  2. Update the Release Notes. Note that each release has a separate page to describe the release, and it's linked from the main page. The individual page lists the changes at a high level (i.e. Updated package X to version Y) and the complete set of RPMs that changed.
  3. Create a ticket on ticket.opensciencegrid.org with a release announcement. Operations will distribute it to the right places.

In addition, we will make another Koji tag/yum repository called osg-release-VERSION. All of the latest packages in osg-release will be tagged to be in this repository, and the tag will be locked. This will give us a reproducible way to install any given OSG Software release.

Moving packages to osg-release-VERSION

When we make a specific release, we copy the osg-release repository to a versioned osg-release-VERSION repository. This allows us to do testing with specific versions and in rare cases allows users to use a specific release.

Moving packages to osg-contrib

The osg-contrib repository is loosely regulated. In most cases, the team member in charge of the package can decide when a package is updated in osg-contrib. Contrib packages should be tested in osg-development first.

Timing of releases

Normally, releases happen on Tuesdays.

Code freezes happen two business days in advance of the release (normally Friday). Specifically: RPM updates intended to be included in the next release (that is, pushed to the osg-release yum repo) must be in the osg-testing yum repo by noon Central Time two business days in advance of the release. This will allow time for final testing, discussions, reverts, etc.

We will make exceptions for urgent situations; consult with the release manager when needed.

CA Certificates and VO Client packages

Packages that contain only data are not part of the usual release cycle. Currently, these are the CA certificate packages and the VO Client packages. Updates to these packages come from the Security Team and Operations Team, respectively. They still move through the usual process for release, and the Software and Release Managers decide when these packages should be promoted to the next repository level. However, the actual releases of these packages do not increment the version number of the software stack.

The release process for data packages is discussed here.